The tortoise and the hare

Well, we’re shuffling our way to the finish line and it’s hard to know whether it’s going to be the tortoise or the hare. Will handover happen before or after I have to go away for three weeks in mid-October? It’s anyone’s guess right now. I am finding it hard to believe we could be done in the next five weeks, but the logistics of this build have been so mind boggling to date that I guess anything’s possible.

Progress this week:
– electrical fit out underway
– plumbing fit out underway
– tiling nearly complete

Getting better all the time

I’m sticking with song lyrics. When you’re on a good thing, you might as well stick with it  😅

The painters and tilers are still cranking it on site, with tradies present both yesterday and today. I had to go to work on both days this weekend so it made me feel less bad that they were at work too  😉

We decided to leave all the wardrobe doors black, as they look very cool in their silver and white homes. All the doors have been rehung so we got a really good idea of how it’s all going to look. We think the dark chocolate floors will help tie it all together, so we are looking forward to seeing those laid (although that’s a few weeks away).

The walls are just about done (there might be one coat to go, but it’s hard to tell) and we love, love, love the blues we picked for our bedroom and our lounge room. The black feature wall in the study looks great. And check our our front door! Another coat to go and it will be done. It’s lairy, all right, but we love it 🙂

The tilers have been back and finished the niche in our shower. It still looks great. So happy with our choices.

Onwards and upwards!IMG_0387

Ooooh, looky, our front door! Yes, folks, the much-vaunted and much-promised Taubman’s Electricity!

IMG_0388

Feature wall in the study in Taubman’s Abyss

IMG_0389

The niche in our shower is done but not yet grouted (which is why it doesn’t look quite right)

IMG_0390

Our gorgeous inky blue bedroom. We’ll have white plantation shutters installed after handover, so the contrast value should be high.

IMG_0391

Black master bedroom doors (1 1/2) looking across the hall to the study.

IMG_0394

A different dark blue in our lounge. That niche will house our vinyl collection and a turntable/stereo. You can also see the electricians have started fitting our gazillions of power points 🙂

IMG_0396

Looking out of the lounge room to the kids’ bedrooms and shared bathroom. You can see all the downlight power points are installed.

IMG_0399

From inside the kitchen across the family room to the kids’ rumpus room.

IMG_0401

From inside the kitchen, looking into the dining room (sliding stackers lead out to the al fresco area) and across to Johnno’s Place.

IMG_0403

Johnno’s kitchen is looking good, so is the bedroom past the extra-wide (wheelchair friendly if we need it later on) door.

IMG_0404

The en suite in Johnno’s Place is just about done. The IXLtastic is in – just need the shower frame, mirrors, taps, toilet, handrails and towel hooks. Wait, that’s a lot to go, isn’t it?

Anyway, great progress.

We hope to see the kitchen splashbacks go in soon, but not before the electricians and plumbers come and do their fit out. We are supposed to deliver the light fittings to the electrician this week. I am pretty excited about seeing the light fittings go in – shit is starting to get real, people!

 

 

 

Getting close to lock up

We had a site inspection with our SS this week and it was great to see the progress:

  • Bricks have been cleaned
  • Water tank has been installed
  • Wet areas have been sealed
  • Floor tiles in wet areas have been positioned
  • Cornice has been delivered and should go up soon
  • Doors have been delivered and should be installed soon
  • Downlight holes have been cut from the Gyprock, including four that shouldn’t have been 😮 (an easy fix, so we are told; when the electricians come back they’ll patch the plaster and affix the battens ready for our hallway pendants)
  • Batten fixtures cord is poking through the ceilings in the right places
  • The concreters have been back to recess the sliding doors but they haven’t been able to dig up the slab they laid in the wrong place for our aircon unit – it’s been so wet they haven’t been able to get the bobcat in through the quagmire that is our front yard

SS thought we’d be at lock up by the weekend so we’ll swing by and check it out!

We also got a call from Don’s Tiles. Two of our choices are no longer available so we had to make the trek over to Mitchell to choose some new ones. New concrete/stone look tiles for our front porch were easy to select. We were advised on Monday that our first new choice was available (and slightly cheaper than the original ones we had chosen). Despite the energetic, helpful and polite assistance from the tile rep, we didn’t have much luck with the tiles for our en suite feature wall (back wall of the shower). We had to pick three new choices as they couldn’t tell us what was in stock/able to be ordered and, to our disappointment, we found out on the following Monday that neither the first two of our choices were available or could be ordered and that our third selection was the only one available – naturally it cost more than our original selection and naturally we picked freaking Carrara marble. It had better look awesome!

So, a general comment: it is 2016. Online stocking systems have been around for more than 20 years. It befuddles us completely that a flooring company holds stock in its showroom that it can’t get. If they can’t get them in, why is the tile still on display? We provided feedback to the SS, as this episode left a slightly sour taste in our mouths; we felt like Don’s Tiles was letting Rawson (and us) down.

We also learned that the Laminex colour we selected for our main kitchen was no longer available. This was a real bummer, as it was a lovely petrol blue and would have complemented the chocolate tones of the bamboo floor and contrasted beautifully with our white Caesarstone benchtops. Fortunately, Polytec now manufactures a ‘woodgrain’ look blue that is close to our original colour selection (a little brighter, perhaps, but given how dark our kitchen is, probably not a bad thing…we will probably need to install a sunlight/diffuser but that will have to wait). So we have gone with Aegean Oak with Ravine finish for the kitchen. This cost us an extra $1k, but we are at that stage in the build that we have spent so much money what’s another thousand? (I die a little every time I say that but they don’t call houses money pits for nothing…)

Anyway, if that’s the worst of it, we will have gotten off lightly with our build. Let’s hope the mudpit that surrounds our house doesn’t cause too many delays. We are still on track for handover late Sep/early Oct.

New photos.

IMG_0018_edited

A big bunch of something (architraves?) in our dining room and family room

IMG_0019_edited

Charcoal tiles for the laundry and the extra storage room we snuck into our modified plans

IMG_0020_edited

Kitchen looking through the family room to the kids’ rumpus

IMG_0021_edited

Hallway (with bonus holes!) looking back to the front door (should be on soon!)

IMG_1557_edited

Our ‘new’ en suite bathroom feature tile. Our fourth choice. Next time I’d exclude feature tiles from the contract and get it done separately so we could work with a company who could guarantee their supply. This marble mosaic had better look good!

IMG_1558_edited

Not new, but it’s nice to see a sample of our bamboo flooring again. In a few more weeks we should see if this choice pays off!

IMG_1565_edited

Our gigantic front door. It’s a timber veneer, but will be painted neon. We’ll be known as the house with the fluoro door 😉

IMG_1567_edited

Our internal doors ready for painting and fitting. They’ll all be painted black.

IMG_1572_edited

Ahoy there! We have a water tank 😀

IMG_1573_edited

Very nice. The Deep Ocean colour works perfectly with the Espresso bricks.

 

 

Brickwork complete and electrical consult done

14Jun16_2_editedThe bricks are done, steel beams are in and the aircon venting has been fitted (although the air intake return is smack bang in the middle of our hallway ceiling and will need to be moved so it’s not an eyesore – our SS has that on his list of things to fix), so there has been some good progress over the past two weeks. We can also see the plumbers have been in fitting black piping and tap points throughout the house. We just need the concreters to come back and rectify two small issues with the slab (they forgot to recess our stacking/sliding doors out to the al fresco and they put the aircon slab under a full height window – both are deviations from the plan so the concreter must rectify at no cost) and we can mark off this stage of the house as complete.

Despite both my other half and I ‘dying’ of the lurgy, we had our consult with the electrician today and what a pleasure he was to deal with. Very professional, had some great suggestions for us about switch placement and options for lighting set ups we hadn’t considered. He’ll also install our pendants if we can provide them to him at fit-out stage so we’ve been ordering light fittings like a couple of crazy kids over the past few weeks. We have no light fittings in our current place (yup, still bare globes after 16 years) so we want to have beautiful lights in the new one. Our porch feature light and main hall lights arrived today and our bedroom light should arrive sometime this week too. We have ordered some gorgeous hand blown glass pendant lights for the kitchen; they should arrive in the next five weeks. Super exciting and we can’t wait to see it all come together over the next couple of months.

14Jun16_1_edited

It was nice to see the brickwork around the front pillars too. They may end up being rendered if we decide the front of the house is a bit dark and we need to introduce some additional contrast. But we won’t know that until the house is finished. There are some things that CAN wait until the build is done 🙂